The Government has paid Shs373.07 billion in compensation to 7,721 project-affected persons (PAPs) to pave the way for the construction of the 272-kilometre Malaba-Kampala Standard Gauge Railway (SGR).
The Minister of State for Works and Transport, Fred Byamukama, told Parliament on Tuesday, November 17, 2026, that the payments had enabled the Government to acquire 2,108 acres out of the 3,536 acres required for the railway corridor.
A total of 12,946 people are expected to be affected by the project, leaving 5,225 yet to receive compensation. Byamukama said the outstanding compensation amounts to Shs472.45 billion and will be paid at a later date.
He noted that land acquisition was most advanced along the Malaba-Mayuge section, where approximately 98 per cent of a continuous corridor had been secured. This provides about 130 kilometres of land on which the contractor can begin construction.
“Compensation and acquisition remain ongoing, with priority given to construction-critical sections,” Byamukama said.
The minister also informed Parliament that the Government had issued a Limited Notice to Proceed (LNTP) to Turkish construction firm Yapı Merkezi to undertake preparatory works as arrangements for financing the full project are concluded.
The LNTP, valued at €75 million (approximately Shs341.63 billion), commenced on May 14, 2025, and was completed in October 2026. Its scope included surveys, geotechnical investigations and procurement of essential equipment, including earth-moving machinery.
Byamukama said the preparatory activities had reduced technical uncertainties and established capacity for the transition to full construction. However, he clarified that the arrangement remains preparatory, pending financial closure and the issuance of a full Notice to Proceed.
Once completed, the Malaba-Kampala SGR is expected to connect Uganda to Kenya’s railway network and the Port of Mombasa, improving access to regional and international markets.
During the parliamentary debate, the Shadow Minister for Works and Transport, Asinansi Nyakato, raised concerns about delays in compensating project-affected persons, arguing that the delays had increased the cost of the project.
Nyakato also asked the minister to explain how climate change risks had been incorporated into the railway project, noting that Parliament had previously resolved that transport infrastructure budgets should provide for climate-related risks.
In response, Byamukama said Shs11 billion had been allocated in the project budget to safeguard the environment, adding that the allocation could be increased if necessary.
Meanwhile, Kassanda County South MP Abdul Bisaso raised concerns about residents living near the railway corridor who fear displacement despite holding legitimate land titles.
Bisaso alleged that Uganda Railways Corporation staff had demarcated some houses located away from land owned by the corporation. He also complained that some demolitions were carried out without adequate notice and without respecting local leaders.
He asked the minister to send a team to conduct a boundary opening exercise to establish the railway reserve and prevent the displacement of residents outside the designated corridor.
Byamukama said the demolitions in Kassanda involved structures found within the gazetted railway reserve. He explained that the exercise was intended to prevent the Government from paying compensation for developments made within land already reserved for the railway.
He added that boundary opening exercises would be conducted in areas where the railway corridor is contested by members of the public.