SHOCKER!! Shs400 Billion Already Spent on Stalled Lubowa Hospital

1 Mins read

The Government has already spent up to 400 Billion Shillings on the stalled Lubowa International Specialized Hospital Uganda.

This was revealed by Henry Musasizi, the State Minister of Finance and Planning in charge of General Duties while appearing before Parliament’s Finance Committee on Wednesday to defend the Ministry’s budget for Financial Year 2022/2023.

Musasizi’s revelation follows the demand by Members of Parliament to provide an update on the construction of the facility which commenced on March 12, 2019.

According to the financial performance brief for the project, Musasizi indicated that the Government paid 234.089 billion in three segments in 2021 while 166.401 billion was paid in two installments in 2022.

This financial year, Musasizi revealed that Government will cash out additional 319 billion shillings, also in two different installments in July 2022. The Direct Agreement indicates approximately 1.3 trillion as of the final project cost of the hospital.

Ramathan Ggoobi, the Permanent Secretary and Secretary to the Treasury said the cost of the hospital also includes medicines for one year; and training of Ugandan health professionals.

Ggoobi disclosed that the project which was due for commissioning in June 2022, has been extended to September 2024 after excessive rainfall between September 2019 – and January 2020 caused a delay in the implementation of the civil works.

Further, Ggoobi also pointed out that the Covid-19 pandemic and the resultant lockdown imposed by the Government from March 2020 until January 2022 caused more delays as ‘efforts to encamp 500 workers on the site were derailed by the continued outbreak of covid-19 among the workers’.

While appearing before the Health Committee of Parliament on Tuesday, Eng George Otim, the Acting Commissioner of Health Infrastructure in the Ministry of Health shocked MPs when he said that Enrica Pinetti the proprietor of the hospital was not at the site.

Eng Otim, who also doubles as the Project Manager for Lubowa International Specialized Hospital at the Ministry of Finance expressed disappointment that he has not been able to supervise the works at the site because the Government failed to allocate funds for the project.

The 264-bed capacity covers 72,000 square metres of Government land located in Lubowa, Wakiso District. Upon completion, the multi-complex facility is expected to save the Government from an annual seepage of 258 billion it spends on medical tourism overseas.

Related posts
News

Uganda Signs Host Country Agreement To Establish African Water And Sanitation Academy

1 Mins read
The Minister of Foreign Affairs, Hon. Gen. Odongo Jeje Abubakhar, today signed the Host Country Agreement with the African Water and Sanitation…
News

Gen. Jeje Odongo Bids Farewell To UNICEF Country Representative

1 Mins read
Hon. Gen. Odongo Jeje Abubakhar, Minister of Foreign Affairs, met with Dr. Munir Safieldin, UNICEF’s outgoing Country Representative for Uganda, as he…
News

Young Herdsman Wins UGX 186 Million In Uganda's National Lotto

2 Mins read
A 20-year-old herdsman from Hima, Kasese District, has experienced a dramatic change in his fortunes after winning UGX 186 million in Uganda’s…